5.3 Cleaning
Personnel:
Cleaning staff
Protective equipment:
Eye protection
Respirator mask
Protective workwear
Protective gloves
Anti-Static Safety Boots
In addition, also follow the separate oper-
ating instructions of the energy supply
Ä
“Applicable documents”.
Requirements:
Material-carrying lines are purged.
Material supply system is switched off and
secured against reconnection.
Material-carrying lines are depressurized.
Mains disconnecting device on the technology
cabinet is switched of
f and secured against
reconnection.
1.
Moisten a piece of cloth or a soft brush with
cleaning agent.
2.
Damp wipe surfaces.
5.4 Maintenance
5.4.1 Maintenance schedule
Interval Maintenance work
Semi-annually
Check that screw connections are seated tightly, re-tighten if necessary.
Annually
Replacing material hoses:
Ä
5.4.3 “Replacing Material Hose”
Replacing compressed air hoses:
Ä
5.4.2 “Replacing Compressed Air Hose”
5.4.2 Replacing Compressed Air Hose
Personnel:
Mechanic
+ additional qualification explosion protection
Protective equipment:
Eye protection
Protective workwear
Protective gloves
Anti-Static Safety Boots
Requirements:
Material supply system is switched off and
secured against reconnection.
Material-carrying lines are depressurized.
Mains disconnecting device on the technology
cabinet is switched off and secured against
reconnection.
Compressed air hose is disconnected from the
atomizer.
Observe separate operating instructions
Ä
“Applicable documents”.
1.
Cut off hose connection.
2.
Fix new compressed air hose on the trimmed
hose using adhesive tape.
3.
Pull out old compressed air hose from the con-
voluted hose at the foot of the robot.
New compressed air hose is drawn in.
4.
Connect hose connection of the new com-
pressed air hose to the atomizer
.
Follow label and diagram.
Cleaning and maintenance
03/2019 Atomizer Connection EcoGun - MRS00004EN 15/24