66
Web page programming
PRC-E Series Instruction Manual MN014003EN August 2015 www.eaton.com
The “Schedules” list screen will now display the schedule
with an Action, “Days”, and a “From” time with the “Until”
time displaying the text “Event”.
Creating a backup schedule
Backup schedules are only used in networked systems with
a master device. In this case, the master device will provide
most of the system scheduling to maintain centralized
control. Master devices include the PRC5000 and the
Ethernet Interface Module (EIM). However, if the network
is down or the master has lost connection, the system will
still have a means of control. The backup schedules are part
of the distributed control feature of the Pow-R-Command
system. If a schedule is flagged as a “Backup” in the PRC-E
Series controller, it will only run when the connection to the
master device has been lost for an extended period of
time. If there is no master device, the controllers will
always be in Backup Mode.
To create a backup schedule, first create the required
schedule following the above procedures.
To specify the schedule as a “Backup”, click the “Backup”
checkbox to add the checkmark.
Click the OK” button to accept the changes.
This schedule is now a backup schedule and will now
display the schedule with a “B” in the “Flag” column of the
list indicating that it is a backup schedule.
Creating holidays
A “Holiday” is a special day that does not follow the
typical daily operational criteria of the system. A holiday
can be selected for any month/day of the year and up to
30 holidays can be created in the PRC-E Series controller.
A 20-character alphanumeric description can be added to
designate the holiday. When a day is selected as a holiday,
it is no longer considered a standard day of a week. For a
schedule to activate on a holiday, a check mark must be
placed in the holiday checkbox.
Selecting a day as a holiday
Click the “Holiday” tab.
This opens the “Holidays” Web page.
The Holiday page has a calendar tool for choosing the date
and also lists the date and description of the date that is
configured as a holiday.
To specify a date as a holiday, use the button at the top of
the screen to choose the month or use the left/right arrows
to scroll through the months.
Click the date required for the holiday.
The date is labeled with “HOL” and placed in the holiday list.
To add a description, click the textbox next to the
date added.
This opens the box for edit.
Type the description of the holiday in the textbox.
Click off of the textbox to accept.
ote:N Since the “Holiday” has only the month and day
specified, it will activate every year on the same
date. Care must be taken managing holidays on the
yearly basis.