ATTENTION: In order to prevent calcification of the heat exchanger, you are advised not
to use hard water, natural spring water instead of mains water.
- Check the domestic water installation by opening the hot water tap. Check for any leaks in the piping.
- The exhaust gas flue assembly must be installed from the original parts in accordance with the instruc-
tions.
- Gas supply must be checked by the qualified gas company.
- Must be called authorized service to start up the boiler after all these processes are completed.
- Commissioning must be strictly performed by authorized service.
-At the end of the commissioning of the device after installation, please ask for information of authorized
service on operating the device and relevant safety devices on device.
10.2- Using the Device
10.2.1- Switching off the Device
Y
ou can switch off the boiler by holding down the ON/ OFF button for 5 seconds. LCD light will
be reduced to %75 after 1 minute. Frost protection remains active.
11- CONTROL PANEL
11.1- Icons of Buttons
The control panel consists of the relevant elements as shown in figure 18 below.
Figure 18