DO 2.1
DO 2.1-10
NP-DO2.1_10_08-2018 - 78 - 08/2018
ANNEX / ANHANG/ ANNEXE / ПРИЛОЖЕНИЕ / ZAŁĄCZNIK / PRÍLOHA / PŘÍLOHA
21. INSTALLATION RECORD
1. Product: (model)
DO 2.1 DO 2.1 T DO 2.1-10 DO 2.1-10 T
DO 2.1 Z DO 2.1 TZ DO 2.1-10 Z DO 2.1-10 TZ
3.2. Address of installation:
4. Equipment connected to the compressor:
5. Installation / Commissioning:
6. Contents of operator training:
A. Product completeness check **
A. Description of the product and functions**
B. Documentation completeness check **
B. Product operation: turning on/off, controls,
control procedures, data on the display
panel, alarms, operation in alarm
conditions**
C. Installation/connection to equipment **
C. Product maintenance: maintenance
intervals, maintenance procedure, service
intervals, operating activities**
D. Safety measures, warnings – their meaning
and compliance **
7. Operator instructed on safety measures, operations and maintenance:
8. Installation and instruction performed by –
First name/Last name
** mark with an “X” in points 5 and 6 (Y - yes /N - no). Enter any observations from points 5 and 6 into the
“Notes” section