66 User Manual THEIA HE-t String Inverters 357115.013, Issue 1.0, 2011 March
8. Maintenance
This chapter explains how to switch OFF and discharge the inverter safely. It also provides an
overview of important regular maintenance procedures to ensure trouble-free operation of the
THEIA HE-t inverters. Finally, it is explained how to remove and return the inverters.
8.1. Switch-Off
Always turn OFF and disconnect the inverter in the following order prior to maintenance
work or repairs:
AC Side
• Turn OFF the AC circuit breaker(s).
DC Side
• Turn OFF the DC switch.
• Disconnect the connectors.
• Discharge the DC capacitor bank (See 8.1.1. Discharge).
DANGER: Never work on live wires!
Never perform work on the inverter without disconnecting both the DC and AC side
because of deadly voltages present at the terminals.
DANGER: Discharge the inverter completely prior to service or
maintenance!
High voltages are still present inside the inverter after switch OFF because of a
charged capacitor bank. It must be discharged before performing service or
maintenance work on the inverter.