Loading...
Servicing valve
Open slightly
Pilot
Screw to set outlet pressure
Outlet valve
Open slowly
Restriction
Set to "RUN" by successive fractions 2, 4 or 6
Servicing valve
Closed
The equipment is commissioned
It is recommended to seal the release relay
Commissioning
Operations concerning the integral slam shut version are in italic.
All interventions on equipment should only be
performedbyqualiedpersonnel
PreliminaryVerications
Start-up positions
Inlet and outlet valves
Closed
Verify the absence of pressure between inlet and
outlet valves
Slam shut valve plug
Closed
Pilot A
Unloaded
Restriction B
START position
Slamshutsetpointverication
Using the atmospheric valve, inject a pressure equal to the
pressure required for the regulator
1
st
release relay stage
Set (Stage 1)
Slam shut valve plug
Open (Stages 2 and 3)
Progressively increase the pressure to
reach tripping
Adjust setting if necessary (D103683X012_OS2_IM)
Note the set point value on the equipment
or mark it on a commissioning document
Positions before commissioning
Impulse line isolating valve
Open
Impulse line atmospheric valve
Closed
Slam shut valve plug
Closed
Servicing valve
Closed
The equipment is ready for commissioning
Commissioning
(Act slowly)
Inlet valve
Open very slowly
1
st
release relay stage
Set (Stage 1)
Slam shut valve plug
Bypass (Stage 2)
Open (Stage 3)
Triggered
position
B20
Stages 2 and 3
Stage 1
Figure 13. Setpoint Verication Phase
B22
Figure 12. Type EZH-OS2 Regulator
INLET PRESSURE
MODULATED PRESSURE
OUTLET PRESSURE
Type EZR
9
Europe, Middle East and Africa Only