EasyManua.ls Logo

ENAR PH60 - Safety During Service; 3 Which Machine Is the most Suitable for each Application

Default Icon
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
TAMPING RAMMERS
en
4
PH60, PH70, PH80
2.3 SAFETY DURING SERVICE
Do not clean or inspect the equipment during operation.
Do not start the motor up with the cylinder flooded or if the spark plug in the petrol motors has
been removed.
Do not inspect the igniter plug to see if it is sparking correctly if the cylinder is flooded with
petrol or in the presence of any petrol fumes.
Do not use dissolvents or fuels to clean the equipment, particularly in closed spaces.
Maintain the area around the silencer clear of inflammable materials.
Before servicing petrol-driven machines, remove the spark plug to guard against the motor
starting up accidentally.
It is not permitted to use the equipment in explosive environments. The fuel tank should be
shut tight. When being transported over long distances, it is highly recommended that the fuel
tank be emptied beforehand.
The transport accessory has not been designed for standing the compaction plate on it and
should only be used to move the equipment.
3 WHICH MACHINE IS THE MOST SUITABLE FOR EACH
APPLICATION?
# Can be used + Recommended
MODEL
APPLICATION
Reversible plates
Non-reversible
plates
Tamping rammers
Patching areas
#
Building foundations
+
Paths and footways
#
Tennis courts and sports areas
#
Soil preparation
+
#
#
Final support for bridge and ramps
+
+
#
Railway junctions
+
+
#
Interlocking cement blocks
#
+
Construction of mains
+
#
+
Construction of drainage
+
+
Compaction of ditches.
+
+
Reparation of damage caused by
broken piping, cables, etc.
# +
Work around piping, cables, drainage,
#
#
+
Filling with rocks
Gravel
+
+
+
Sand or volcanic material
+
+
#
Mixed grounds
+
#
+
Mud
+
+
Clay
+
+
Layer thickness 0 – 25 cm
+
+
+
Layer thickness 20 40 cm
+
+
Hot mortar
#
+
#
Cold mortar
#
+
#
Subgrade 40 100 mm
+
#
+
Layer of boulders 25 60 mm
#
+

Table of Contents