C3 Installing the Horizontal Power Flue
Note: The appliance is designed only to operate using the approved
exible or PolyPro ue supplied by Escea. Other brands of ue may
not t, and this will aect the appliance warranty.
The Horizontal Power Flue Wall Terminal must be installed in the
correct orientaon (the small horizontal slot should be at the
boom). This allows for the correct operaon of the ue system
and prevents the ingress of water.
The Horizontal Power Flue Wall Terminal must be weather ght
when installaon is complete to prevent damage to the dwelling. It
must be installed by a suitably qualied person.
Fit the Horizontal Power Flue Wall Terminal into the hole and x in
place, making sure the installaon is sealed appropriately to prevent the ingress of water from outside the wall
cladding. Take noce of the label on the terminaon which shows the correct orientaon of the terminal.
Note: It is the responsibility of the installer to ensure the Horizontal Power Flue Wall Terminal is installed to all
relevant building codes to ensure weather ghtness.