6
Operation and Maintenance Instructions
OPTIONAL ACCESSORIES:
6. Coupling/Shaft Inspect flex elements and
hardware for tightness, proper torque &
crack/deterioration monthly
7. Heater Controller Inspect controller and
clean probe ends quarterly
8. Heater Inspect junction box for loose wiring
and moisture one month after start-up and
semi-annually
9. Heater Inspect elements for scale
build-up quarterly
10. Electronic Water Level Controller Inspect
junction box for loose wiring and moisture
semi-annually
11. Electronic Water Level Controller Clean
probe ends of scale build-up quarterly
12. Electronic Water Level Controller –Clean
inside the standpipe annually
13. Solenoid Make-up Valve Inspect and clean
valve of debris as needed
14. Vibration Switch (mechanical) Inspect
enclosure for loose wiring and moisture
one month after start-up and monthly
15. Vibration Switch Adjust the sensitivity
during start-up and annually
16. Sump Sweeper Piping Inspect and clean
piping of debris semi-annually
17. Water Level Indicator Inspect and clean
annually
1. Few Days: Energize motor space heaters
when motor is idle
2. Few Weeks: Run gear reducer for 5 minutes
weekly
3. Several Weeks: Completely fill gear reducer
with oil. Drain to normal level prior to running.
4. One Month or longer: Rotate motor shaft/fan
10 turns bi-weekly
5. One Month or longer: Megger test motor
windings semi-annually
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
DURING IDLE PERIODS:
MAINTENANCE
CHECKLIST