Plus 12 Operator's Manual (164200090 Rev E)   33
8 Installation
The following sections describe your UPS package and the installation and physical
setup of the UPS, optional Power Distribution Module (PDM), and remote batteries.
Unpacking and Inspection
Upon receiving your UPS, optional battery cabinet(s), or PDM, carefully examine the
packing containers for any signs of physical damage or leakage. Notify the carrier
immediately if damage is present.
Carefully unpack the UPS and battery cabinets, making sure you retain the packaging
materials for future shipment of the units. Examine each unit carefully. Immediately
notify your distributor if you find any damage. Do not operate any unit that is leaking
liquid, or if a white, powdery residue is present.
Site Preparation
For optimum system operation, be sure that your site conforms to the following
specifications and requirements:
The maximum elevation for normal operation is 5000 ft (1500 m). Derating is
required for higher elevations.
Equipment weights are provided for typical configurations (see page 30). Contact
your local sales representative if additional information is needed.
Additional battery cabinets may be added for extended battery time.
The unit should be installed with these environmental specifications: operating
temperature of to 40°āC and humidity of 5% to 95% (noncondensing).
Important Safeguards
Do not tilt the cabinet more than 12 degrees; the unit may tip over.
Do not connect more than three battery cabinets to the UPS unit to avoid fire and
electrical shock hazard.