CHAPTER 20
PAGE 14
EXT
RA - FLUGZEUGBAU GmbH
SERVICE MANUAL EXTRA 200
PAGE DATE: 1. July 1996
18 Install propeller in accordance with MT-Propeller in-
stallation instructions E-124 latest revision.
19 Remove tail weight.
20 Check if all switches are in Off-position and connect
battery.
21 Perform operational check of electrical equipment.
Shut-off master switch after completion.
22 Perform operational check and rigging of control sys-
tem.
23 Inspect fluid filled lines for leaks.
24 Check security of main spar bolts.
25 Install wheel fairings, main fuselage cover and rear sup-
port angle, canopy, engine cowlings, and access pan-
els (Refer to Chapter 51-00-01 and 53).
26 Check all control surfaces for freedom of movement
and security.
27 Perform a compass compensation according to Air-
craft Inspection and Repair FAA AC 43.13.
28 Check correct servicing of aircraft.
29 Perform an engine run up. Refer to Chapter "05-20-04
Scheduled Maintenance Checks". Start the engine in
accordance with the Pilots Operating Handbook and
Airplane Flight Manual (POH).
30 Inspect aircraft for foreign objects.
31 Final inspection by licensed aircraft inspector.
I M P O R T A N T After first flight check fuselage interior/exterior for fuel
leaks. Check all bolts on fairings and cover sheets for
tight fit.
ASSEMBL
Y INSTRUCTION
Assembly Instruction after Container Shipping