P P C
PROGRAMMING
GUIDE
FOR
PPC6000
SERIES
DESCRIPTION:
This document supplies the commissioning engineer with sufficient information to make
appropriate setup and changes to the commissioning of the PPC6000.
NOTE: For additional information on Installation and Wiring information, please
refer to the complete installation manual - Fireye bulletin PPC-6001
For ease of navigation (see section 1.3.1), the symbols below will be used throughout
the Commissioning Process in this manual to indicate the correct application for each
commissioning OPTION, for use by the Commissioning Personnel.
A convenient check box has been added to the beginning of the symbols so that the
Commissioning Personnel can mark each appropriate option as it is completed.
SYMBOL MEANS:
Commissioning Personnel MUST execute this option
For Customers with O2 TRIM option, Commissioning
Personnel MUST ALSO execute this option
For Customers with VFD options, Commissioning Personnel
MUST ALSO execute this option
NXPG-6001
APRIL 8, 2013
P P C
O 2
V F D
After each appropriate option parameter is
complete, CHECK THE BOX!