5CS2006OM (rev 00 07/2020) 18
for leaks.
4. Prepare to spray by turning section control
valves to OFF.
5. Start tractor and engage PTO. For adequate
spraying pressure and tank agitation, PTO
should be running at or near 540 rpm.
Ensure pump is primed and there are no
leaks in any lines.
6. Use relief valve to adjust sprayer pressure
to pressure rating determined during sprayer
calibration. When opening control valve, it
may be necessary to adjust pressure again.
7. Ensure that tractor PTO is disengaged. Fill
tank with amount of water and chemicals
recommended by chemical being used. After
lling tank, engage pump and allow ample
amount of time for jet agitator to mix water
and chemicals.
NOTE: Do not start sprayer operation
until chemicals and water are mixed for the
recommended time listed on the chemical
instructions.
8. At spraying location, unfold the boom at
locations away from hinges.
9. Engage PTO, and make sure pressure
setting is correct. While spraying, maintain
a constant level of speed and rpm (rates
determined when calibrated).
10. When complete, fold boom back into
transport position.
Boom Section Control 12.5 ft and Boomless
The Boom is divided into 3 sections of spray
tips. Right, Center and Left. The Left and Right
sections can be turned on and off by turning the
corresponding in-line valve on the boom.
12.5 ft Boom Spray Width
• 30 inches - Both left and right sections OFF.
• 90 inches - Either left or right section OFF.
• 150 inches - Both left and right sections
ON.
Boomless Spray Width
• 2.5 ft - Both left and right sections OFF.
• 12 ft - Either left or right section OFF.
• 24 ft - Both left and right sections ON.
Boom Section Control 18 ft Boom
The Boom is divided into 3 sections of spray
tips. Right, Center and Left. Each section can
be turned ON and OFF individually using the
boom section control valves.
1. To turn a section ON move the
corresponding handle to the horizontal
position.
2. To turn a section OFF move the handle to
the down position.
• Right Section (A), Center Section (B),
Left Section (C)
Operation
A B C