2.2.7 Stability check by primary injection
Restricted earth fault
Phases
Primary current
(A1)
Spill current
(A2)
A
N
B–
N
C
N
Circulating current between two or more sets of current transformers.
Phases
Primary current
(A1)
Spill current
(A2)
A1
A2
B1
B2
C1C2
Where more than two sets of current
transformers
are involved, injection should
be carried out between set 1 and each other set in turn.
Commissioning
Engineer
Customer
Witness
Date Date
22