Model
SIE-L2
Description
Generator Interlock Kit for Siemens Left column Main 150-200 Amp
Main Breaker
150 or 200 amp single handle Horizontal throw Right (on) Left (off)
Generator Breaker
Top right side 2 positions
WARNING
Only qualified personnel should be working on the panel box
An amateur should NEVER open the panel box
Please follow all rules and regulations of the National Electric Code
Step 1: Disassemble the interlock. Place the bottom plate (holes only) from edge of main breaker to bottom edge of generator breaker
Step 2: Turn off main breaker and remove panel cover.
Step 3: Drill holes as marked on panel cover with supplied 3/16 drill bit and remove all burs from drilling cover.
Step 4: Insert screws from rear of cover, install bottom plate, and install top plate (slotted) install retaining nuts, and thread lock. And
Ensure proper movement.
Step 5: Install 2 pole Generator breaker on top right side and place Generator Warning Sticker on Generator breaker.
Step 6: Combine 2 zip ties and install zip tie under metal plate and around top of breaker as shown in picture below. Pull on ends to
make tight around breaker and trim ties as needed. Install warning label on zip ties next to breaker.
Question and Answer IconNeed help?

Do you have a question about the GenInterlock SIE-L2 and is the answer not in the manual?

Summary

General Safety Warning

Qualified Personnel Required

Only qualified personnel should work on the panel box.

Amateur Restriction

An amateur should NEVER open the panel box.

NEC Compliance

Follow all rules and regulations of the National Electric Code.

Installation Guide

Step 1: Disassemble and Position Bottom Plate

Place bottom plate from main breaker edge to generator breaker edge.

Step 2: Turn Off Main Breaker and Remove Panel Cover

Turn off main breaker and remove the panel cover.

Step 3: Drill Holes and Deburr Panel Cover

Drill marked holes on panel cover and remove all burs.

Step 4: Install Interlock Plates and Secure

Install bottom and top plates, secure with nuts and thread lock.

Step 5: Install Generator Breaker and Warning Sticker

Install 2-pole generator breaker and place warning sticker.

Step 6: Secure Breaker with Zip Ties

Use zip ties to secure breaker around metal plate and top.

Step 7: Re-install Cover and Verify Operation

Re-install panel cover, verify interlock operation.

Step 8: Place Caution and Start-Up Labels

Place generator start-up and caution labels on panel box.

Disclaimer and Support

Installation Responsibility

GenInterlock.com is not responsible for misuse or improper installation.

Contact for Support

Contact sales@GenInterlock.com for support if interlock fails.

GenInterlock SIE-L2 Specifications

General IconGeneral
Rated Current16A, 20A, 25A, 32A, 40A, 50A, 63A
Rated Voltage230/400V AC
Breaking Capacity6 kA
Trip CharacteristicsC Curve
Mechanical Life20, 000 operations
Electrical Life10, 000 operations
Operating Temperature-25°C to +55°C
Storage Temperature-40°C to +70°C
Terminal TypeScrew Terminals
StandardsIEC/EN 60898-1, IEC 60947-2
MountingDIN Rail