Model
SIE-P2
Description
Generator interlock kit Siemens and Murray 150-200 Amp Panel
Plug on Neutral and Non Plug on Neutral
7/8 to 1 ¼ Spacing
Main Breaker
150 or 200 amp single handle Horizontal throw Right (on) Left (off)
Generator Breaker
Top right side 2 positions
WARNING
Only qualified personnel should be working on the panel box
An amateur should NEVER open the panel box
Please follow all rules and regulations of the National Electric Code
Step 1: Disassemble the interlock. Place the bottom plate (holes only) and follow cutout of the main breaker as in picture
Step 2: Turn off main breaker and remove panel cover.
Step 3: Drill holes as marked on panel cover with supplied 3/16 drill bit and remove all burs from drilling cover.
Step 4: Insert screws from rear of cover, install bottom plate, and install top plate (slotted) install retaining nuts, and thread lock. And
Ensure proper movement.
Step 5: Install 2 pole Generator breaker on top right side and place Generator Warning Sticker on Generator breaker.
Step 6: Combine the zip ties to make a loop and install zip ties around top set of breakers in panel as shown in picture on the next
page. Pull on ends to make tight around breakers. Trim zip ties as needed and install Warning label next to release tab on zip
tie at generator breaker.
Question and Answer IconNeed help?

Do you have a question about the GenInterlock SIE-P2 and is the answer not in the manual?

GenInterlock SIE-P2 Specifications

General IconGeneral
Storage Temperature-40°C to +70°C
Rated Current16A
Dielectric Strength2kV
Humidity95% RH
Terminal TypeScrew type
Mounting TypeDIN rail

Summary

Generator Interlock Kit Installation Steps

Step 1: Disassemble and Prepare

Disassemble the interlock, place the bottom plate, and follow the main breaker cutout.

Step 2: Panel Preparation

Turn off the main breaker and remove the panel cover.

Step 3: Drilling Holes

Drill holes as marked on the panel cover with the provided drill bit and remove burs.

Step 4: Plate and Component Installation

Install screws, bottom plate, top plate, retaining nuts, and thread lock for proper movement.

Step 5: Breaker and Sticker Placement

Install the 2-pole generator breaker and place the Generator Warning Sticker.

Step 6: Securing Breakers with Zip Ties

Use zip ties to secure breakers, tighten, trim, and install the warning label.

Step 7: Final Verification

Re-install panel cover and verify proper interlock operation for both breaker states.

Step 8: Label Placement

Place generator start-up procedure and caution labels on the panel box and meter pan.