1-800-637-9508 page 5
Step 6 - Completing the Add-On Unit
Assemble
the top Long Double
Rivet Beams
to the top two keyholes of the Angle Post.
Assemble the two Long Double Rivet Beams
at the 7
th
-8
th
to keyhole. Hit all Beams to
lock.
COMPLETION WORKBENCH
Add Post Caps (Item 5) to the top eight exposed
Angle Posts. Refer to detail B.
Lay Shelf Decks into place.
Congratulations on your completed work
bench!
Step
8 - Completion
ADD ON UNIT WORKBENCH
Tie Pins (Item 6) may be used to fasten the
primary end and add on unit together.
Refer to detail A.
Step
7 - Tie Pins
A
B
Tie Pin