Gree GMV6 DC Inverter VRF Units Service Manual
Note:
During commissioning, users must listen to the operating sound of outdoor and indoor fans and
compressors to check for exceptions.
3.2.5 Unit Commissioning by Using Multi-functional Debugger
Step 1:
Connect multi-functional debugger. For details, see the user manual of multi-functional
debugger.
Step 2:
Set the address DIP switch (SA8) of the master outdoor unit to 00. Otherwise, it is invalid.
Step 3:
Click
Unit Debug
on the home page to enter the commissioning page.
Step 4:
On the commissioning page, click
Startup
to start commissioning or click
Stoppage
to stop
commissioning.