4.3.3 Test of Drainage System
(1) Please test drainage system after electric work is finished. Inject approximately 1L
purified water to drain pan from air vent, ensure that not to splash the water over the
electrical components (e.g. water pump. etc.).
(2) During the test, please carefully check the drainage joint and make sure no any leakage
occur.
(3) It’s strongly recommended to do the drain test before ceiling decoration.
Ceiling type
Fig.4.3.3.1
Floor type
Fig.4.3.3.2