GREE U-Match 5 SERIES UNIT SERVICE MANUAL
113
Removal of electronic expansion valve
Note: Before removing the electronic expansion valve, make sure there is no refrigerant in the pipeline and power is cut off.
Step
Picture
Work instruction
5. Install the new
electronic expansion
valve.
Weld the connection pipe of
electronic expansion valve.
When welding the electronic
expansion valve, the valve should
be wrapped with wet cloth.
Nitrogen welding: the pressure of
nitrogen is 0.5±0.1kgf/ c
(relative pressure). Note: When
welding the pipes, do not let the
flame burn the other components.
Install the coil of electronic
expansion valve.
6. Secure the electric box
and arrange the wires as
required.
Put the electric box back in place
and tighten up the screws.
Arrange the wires as original.
7. Check and open the
upper and side panels.
Check whether each component
and connection wire is well
connected.
If everything is OK, install the
upper, left and right panels.
Tighten up the screws.

Table of Contents

Other manuals for Gree GUD50T/A-T

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Gree GUD50T/A-T and is the answer not in the manual?

Gree GUD50T/A-T Specifications

General IconGeneral
BrandGree
ModelGUD50T/A-T
CategoryAir Conditioner
LanguageEnglish

Related product manuals