17
All settings both on boiler and
burner will be recorded on a
commissioning report which
will be supplied to the
customers representative.
Commissioning Report
Commissioning
commissioning is in accordance with burner makers requirements.
controls are proved and stats are adjusted in line with temperature indicated on the
boiler thermometer.
that the boiler is red up at a rate allowing the door refractory to reach a uniform
temperature through its thickness thereby preventing any damage.
burner is adjusted to give optimum combustion, together with flame shape and
penetration.
the Heating Engineer will have the opportunity to receive instruction on the correct
operation of the plant during commissioning and to aquaint himself with the fault nding
chart on pages 23-26. He will also be advised on how much of the ‘action’ columns
can be dealt with by site staff.
August 2014