C. Freeze Protection (When Used)
1. Determine the freeze protection uid quantity using total
system water content following the uid manufacturers
instructions. Remember to include expansion tank water
content.
2. Local codes may require back ow preventer or actual
disconnect from city water supply.
3. When using freeze protection uid with automatic ll, install
a water meter to monitor water makeup. Freeze protection uid
may leak before the water begins to leak, causing concentration
to drop, reducing the freeze protection level.
NEVER use automotive or standard glycol antifreeze. Do
not use ethylene glycol made for hydronic systems. Use only
freeze-protection uids certied by uid manufacturer as
suitable for use with stainless steel boilers, veried in the uid
manufacturer’s literature. Thoroughly clean and ush any
system that has used glycol before installing the new boiler.
Provide the boiler owner with a material safety data sheet
(MSDS) on the uid used.
D. Fill and Test Water System
Ensure the boiler is full of water before ring the burner. Failure
to do so will damage the boiler. Such damage IS NOT covered by
warranty, and could result in property damage, severe personal
injury, or death.
1. Fill the system only after ensuring water chemistry meets the
requirements listed in this manual.
2. Close the manual and automatic air vents and boiler drain
valve.
3. Fill to the correct system pressure. Correct pressure will vary
with each application.
a. Typical cold water ll pressure for a residential system is 12
psi.
b. Pressure will rise when boiler is turned on and system water
temperature increases. Operating pressure must never exceed
the relief valve pressure setting.
4. At initial ll and during boiler startup and testing, check
system thoroughly for leaks. Repair all leaks before proceeding
further.
Eliminate all system leaks. Continual fresh make-up water will
reduce boiler life. Minerals can build up in the heat exchanger,
reducing heat transfer, overheating the heat exchanger and
causing heat exchanger failure.
5. The system may have residual substances that could aect
water chemistry. After the system has been lled and leak
tested, verify that water pH and chlorine concentrations are
It is important to purge the system of air to avoid damage to
the boiler.
E. Purge Air from Water System
1. Purge air from the system:
a. Connect a hose to the purge valve and route hose to an
area where water can drain and be seen.
b. Close the boiler or system isolation valve between the
purge valve and ll connection to the system.
c. Close zone isolation valves.
d. Open quick-ll valve on cold water make-up line.
e. Open purge valve.
f. Open the isolation valves one zone at a time. Allow water to
run through the zone, pushing out the air. Run water until no
noticeable air ow is present. Close the zone isolation valves
and proceed with the next zone. Follow this procedure until
all zones are purged.
g. Close the quick-ll water valve and purge valve and
remove the hose. Open all isolation valves. Watch the system
pressure rise to correct cold-ll pressure. It is recommended
that you put the pumps into manual operation to assist in
purging the circuits.
h. Disconnect the wires that are connected to the
THERMOSTAT terminals of the customer connection
board. Apply power to the boiler. The display will show
the temperature of the water in the boiler. Press the v and
ENTER keys simultaneously and hold for 1 second. The
display will read:
The central heating pump will come on. If you then press the
^ key, the central heating pump will shut o. The display will
read:
PROPANE BOILERS ONLY The propane supplier mixes an
odorant with the propane to make its presence detectable. In
some instances the odorant can fade, and the gas may no longer
have an odor. Before startup (and periodically thereafter), have
the propane supplier verify the correct odorant level in the gas.
The DHW pump will come on. If the boiler is set up as a
cascade master and you then press the ^ key again, the
DHW pump will shut o. The display will read:
The system pump will come on. Use the ^ and v keys to toggle
between running each pump in the system as required to
help bleed out all entrapped air. Some good indicators that
air is removed include the absence of gurgling noises in the
pipes and pump operation becoming very quiet. Pressing ^
and v together at any time will return the boiler to normal
operation.
i. After the system has operated for ve minutes, eliminate
any residual air by using the manual air vents located
throughout the system.
j. If purge valves are not installed in the system, open manual
air vents in the system one at a time, beginning with the
lowest oor. Close vent when water squirts out. Repeat with
acceptable by sample testing.

Table of Contents

Other manuals for HTP EFT-110

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the HTP EFT-110 and is the answer not in the manual?

HTP EFT-110 Specifications

General IconGeneral
BrandHTP
ModelEFT-110
CategoryBoiler
LanguageEnglish

Related product manuals