LP-293 Rev. 9.24.15
23
NOTES:
1. This drawing is meant to show system piping concept only.
2. Install a minimum of 12 diameters of straight pipe upstream of all circulators.
3. Piping shown is Primary/Secondary.
4. System ow (secondary loop) should be greater than the boiler primary loop ow. In all cases, the boiler primary loop ow rate must be
maintained above the minimum ow rates published in this manual.
5. Installations must comply with all local codes.
6. In Massachusetts, a vacuum relief valve must be installed in the cold water line per 248 CMR.
The piping will not support the weight of the circulators. Refer to the circulator manufacturer’s instructions to properly support
the circulator. Failure to comply with these instructions could result in property damage, severe personal injury, or death.
Figure 10 - Cascaded Space Heating
Primary
Loop
Primary Loop
Secondary Circuit