Installation Sequence Subcategory Item Diagram ID Diagram Name
Removing the Sealing Plates at the Bottom of Pre-fab.
Modules
NO.S001
Pe-fab. Module Bottom Sealing Plate
Removal Position Diagram
Determining the Pre-fab. Module Installation Position
Removing the Pre-fab. Module Cover
Hoisting and Securing Pre-fab. Modules
Grounding Pre-fab. Modules Grounding Pre-fab. Modules NO.S003 Pre-fab. Module Grounding Position Diagram
Installing Awnings Installing Awnings Installing Awnings NO.S007 Awning Installation Position Diagram
Installing Drainpipes
Installing Water Refill Pipes
Removing Transport Protection Materials for Fire
Extinguishing Devices
Removing Air Conditioner Compressor Fasteners
Removing the Liquid Level Detector Fastener
Checking the Connection of the Interconnection Terminal
of the Low Liquid Level Detector
Removing the IT Cabinet Sliding Base Fasteners
Removing the Sliding Door Fasteners
Installing the IP6X Dustproof Module Installing the IP6X Dustproof Module N/A N/A
NO.P006 Lithium Battery Installation Diagram
NO.P007
Lithium Battery Cabinet Battery Module and
Cable Installation Diagram
Installing UPS Power Modules NO.P008
UPS5000-E-800K-FM Power Module
Installation Position Diagram
Installing Air Conditioner Outdoor Units
Connecting Power Cables to Air Conditioner Outdoor
Units
NO.P003 Outdoor Unit Power Cable Wiring Diagram
Installing Monitoring Devices Installing ECC800 Antenna NO.M004
Monitoring Device Installation Position
Diagram
Monitoring Onsite Wiring Diagram Monitoring Onsite Wiring Diagram NO.M005 Monitoring Onsite Wiring Diagram
Fire Extinguishing Onsite Wiring Diagram Fire Extinguishing Onsite Wiring Diagram NO.F006 Fire Extinguishing Onsite Wiring Diagram
Installing CE-Certified Fire Extinguishing Devices
Installing Batteries
NO.P009 UPS Bottom Incoming Cable Wiring Diagram
NO.P011 External Cable-UPS Wiring Diagram
NO.P012 External Cable-PDF Wiring Diagram
Checklist of Devices Installed Onsite
Installing Pre-fab. Modules
Connecting External Cables Installing External Input Power Cables
Installing Pre-fab. Modules (Concrete Platform Solution)
Installing Lithium Batteries
Installing External Input Power Cables
Installing External Air Conditioner Pipes
Installing Power Supply and Distribution Devices
Installing Fire Extinguishing Devices
Fire Extinguishing Device Installation Position
Diagram
NO.F004
Pre-fab. Module Pipe Installation Position
Diagram
NO.S002
Pre-fab. Module Installation Position Diagram
N/AN/AN/A
Installing Devices Inside Pre-fab. Modules
Removing Transport Protection Materials
NO.S004Installing External Air Conditioner Pipes