17
2. Install the 110 V switch.
3. Connect the live wire
(corresponding to cable 2056)
and neutral wire (corresponding
to cable 2055) from the upper
end of the switch to positions 1
and 2 of the XT9 terminal block.
Connect the live wire
(corresponding to cable 1751)
and neutral wire (corresponding
to cable 1752) from the lower
end of the switch to the socket.
Connect the live wire (corresponding to cables 1757) and neutral wire (corresponding
to cables 1760) from the lower end of the terminal block to the socket.
Scenario 2: Installing a 220 V Socket
No.
Meaning
1
110 V
switch
installation
position
1. Connect the live wire and neutral
wire from the mains to positions 1
and 2 of the XT9 terminal block.
No.
Meaning
1
110 V/220 V socket
installation position
Scenario 1: Installing a 110 V Socket
1. Select a 110 V or 220 V socket as required.
2. Connect the live wire and neutral wire.