19
(Optional) Connecting Socket Cables
5.3
Cables 1755, 1758, 2066, 2065, 1761, and
1766 are pre-installed. Cables 1756, 1751,
1759, 1752, 1757, 1763, 1760, 1765, 1762,
and 1764 need to be installed.
The cables to be installed can be obtained
from the cable binding position shown in
the figure.
No.
Meaning
1
Cable binding
position
1. Select a 110 V or 220 V socket as required.
2. Connect the live and neutral wires.
Scenario 1: Installing a 110 V Socket
1. Connect the live wire
and neutral wire from
the mains to positions
1 and 2 of the XT9
terminal block.
This procedure applies only to the models listed in the table below.
Model
Air Conditioner Position in the Battery Cabin
LUNA2000
-2.0MWH-1HX
1/2/4/5/7/8/10/11
LUNA2000
-2.0MWH-2HX
1/3/5/7/9/11
LUNA2000
-2.0MWH-2HX
2/4/6/8/10/12