EasyManua.ls Logo

Huawei PDU8000 Series - Installation Preparations; Technical Documents

Huawei PDU8000 Series
19 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
3
For details about the MDU, monitoring board module, and the operation methods, see PDU8000
Modular Precision PDC User Manual (1100 mm Deep).
NOTE
Monitoring Board Module
(1) Indicator
Indicator Status
Description
Blinking green slowly
The monitoring board is running properly.
Blinking green fast
The communication fails. The MDU generates a monitoring
board communication failure alarm.
Blinking red
Power supply to the monitoring board is faulty and there is a
surge current impact alarm.
Off
The monitoring board is not working.
2
Installation Preparations
1. This document describes the process for installing the modular precision power distribution
cabinet (PDC). Before installation, read PDU8000 Modular Precision PDC User Manual (1100
mm Deep) to learn the product information and safety precautions.
2. Use insulated tools during installation and operation.
3. Only engineers certified by the manufacturer or its agents are allowed to perform PDU8000
installation, commissioning, and maintenance. Otherwise, personal injury or equipment
damage may occur, and the resulting PDU8000 faults are beyond the warranty scope.
4. Sections and steps marked as optional in this document can be performed selectively based
on the actual configuration.
Technical Document
Function
Obtaining Method (Remarks)
BOM
Describes the product
configuration.
Delivered with the PDC.
PDU8000 Modular
Precision PDC User
Manual (1100 mm
Deep)
Describes the features,
installation, operation, and
maintenance of the PDU8000 in
detail.
Downloaded from
http://support.huawei.com
Downloaded from
http://support.huawei.com/enterprise
Technical Documents2.1

Other manuals for Huawei PDU8000 Series

Related product manuals