Page #21 background imageLoading...
Page #21 background image
20
5
Verifying the Installation
1.
The SUN2000 is installed correctly and securely.
2.
The DC switches and downstream AC switch are OFF.
3.
All ground cables are connected securely, without open circuits or short circuits.
4.
AC output power cables are connected correctly and securely, without open circuits or short
circuits.
5.
DC input power cables are connected correctly and securely, without open circuits or short
circuits.
6.
The RS485 communications cable is connected correctly and securely.
7.
The maintenance compartment door is closed and the door screws are tightened.
8.
Unused DC input terminals are sealed.
9.
Unused USB ports are plugged with watertight caps.
Connecting Communications Cables (48 mm Two-Hole Rubber Plug)
If three communications cables are to be connected, use the three-hole rubber plug that is
bound in the maintenance compartment.

Other manuals for Huawei SUN2000-200KTL-H2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei SUN2000-200KTL-H2 and is the answer not in the manual?

Huawei SUN2000-200KTL-H2 Specifications

General IconGeneral
BrandHuawei
ModelSUN2000-200KTL-H2
CategoryInverter
LanguageEnglish

Related product manuals