EasyManua.ls Logo

IBM Power System 5105-22E

IBM Power System 5105-22E
112 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Figure 76. Reconnecting the signal cable and the power cable
3. Replace the air baffles. For instructions, see Replacing the air baffle (www.ibm.com/support/
knowledgecenter/POWER9/p9haj/p9haj_922_airbafflereplace.htm).
Preparing the 5105-22E, 9008-22L, 9009-22A, 9009-22G, or 9223-22H system for
operation after removing and replacing the drive backplane signal cable
To prepare the system for operation after removing and replacing a drive backplane signal cable,
complete the steps in this procedure.
Procedure
1. Slide the service access cover (A) onto the system unit.
2. Close the release latch (B) by pushing it in the direction shown.
84
Power Systems: Power Systems: Drive backplane

Table of Contents

Related product manuals