58
9.3 PLANNED MAINTENANCE
General test (to be carried on using the equipment accessories of the machine): pressure, temperature, electric absorption, regu-
lation of the detergent ow. Times of maintenance and replacement of the components are calculated in multiples of 250 hours,
so that interventions become standard and you have a programmed maintenance of the pressure washer. If we ll a schedule with
the components that need maintenance or replacement in order of the usage (250, 500, 750, 1000 hours), the result you will get is
a plan of programmed work, as follows in the enclosure.
Service at 250 hours
Check Components Replace Clean Set
In line fuel lter
Fuel pump lter
Electrodes
Burner combustion
Fuel pressure
Unloader valve
Safety valve
H.p. nozzle
Quick couplings
Inlet water lter
Pump oil (1
st
time) after 50 hours
Service at 500 hours
Check Components Replace Clean Set
Pump valves
Seal packing
In line fuel lter
Fuel pump lter
Fuel nozzle
Electrodes
Spark plug
Fuel tank
Burner combustion
Fuel pressure
Unloader valve
Safety valve
H.p. nozzle
Quick couplings
Inlet water lter
9 MAINTENANCE
Copyright ©2016 Idrobase Group. All rights reserved.