BPD series PV pumping inverter Installation guide
59
About 10 mm
Figure 5.14 AC connector cable installation
(4) Tighten the connection part on the left side of the connector.
Figure 5.15 AC connector assembly
(5) Tighten the rear part of connector.
Figure 5.16 Assembled AC connector
5.4.3 GPRS module installation
The GPRS module is optional, and currently is supported only by BPD004TNAC and
BPD2K25K5TRAC(S). If a GPRS module is required, connect it to the "GPRS"
interface, see Figure 2.2 (b), of the inverter. Figure 5.17 shows the connection. For
details about how to use the GPRS module, see the user manual delivered with it.