BPD series PV pumping inverter Commissioning guide
68
6.5 Flow chart of the commissioning
3PH pump
motor
Power up the BPD
inverter after the wiring
is checked to be okay
P00.18=1
1PH pump
motor whose
capacitors can
be removed?
P02.00=0
Set pump
motor
parameters
Water
pumping
status okay?
Run
automatically
?
P00.01=1P05.01=1
Run manually:
P00.01=1, P05.01=0,
P05.04=1, Close S4
P00.13=1
P02.00=1
P04.34=0x01
Set pump
motor
parameters
P02.00=1
Set pump
motor
parameters
Y
N
Y
N
Y
N
Y
N
PV Input only?
P15.29=2
AC Input only?
P15.29=1
PV/AC Auto switch:
P15.29=0
Hit "Run" on
Keypad
P02.04=200
Y
N N
Y
Start
End
Figure 6.4 Commissioning flow chart