Figure 4
The display shows the gas quantity to be charged
(default value: 2000 g). Adjust the desired quantity by
pressing UP/DOWN, keeping in mind that about further
500 grams of gas will be automatically added due to fluid
recovery from station internal circuit.
Confirm the value by pressing OK. The station will start
gas RECOVER from external tank, automatically
stopping once reached the set quantity, and will ask to
close the external tank valve (do it).
A de-icing pause is executed for about 3 minutes.
The station returns to AUTO mode. Gas tank refilling
operation is done.
7. Fill the new oil container ( see paragraph 3.7).
8. Open the quick couplings (see Figure 1).
9. Open the station RED and BLUE valves.
10. Preparation procedure is done.