SERVICE MANUAL
E-125
Fig.7
10. Once you have chosen and inserted suitable shim (14) with chamfer against the gear, force bearing cone (13) into the
pinion shaft (15) using special tool CA716171. Assemble pinion assy to the transmission.
See: fig.7 and sec. E.1 (Gear box).
11. Assemble inner cup of the bearing (11) into the box (12).
12. Assemble following group (g): gear (10), ring nut (9), thrust washer (8), bearing needles (6) and (7), gear (5), spacer (4),
collar (3), central clutch (2) and thrust washer (1).
Note: right position for central clutch (2).
See: fig.9.
Note: grease thrust washers (8) and (1) so that they do not fall on the gear box.
See: fig.10 and 11.
13. Settle group (g) into the gear box (12) and insert pinion (15) into the box (12) and in the group (g).
See: fig.8 and 9.
Fig.8
See: fig.6.
8. Choose shim (14) with thickness value (S) among range available and fit it on the shaft under the pinion head.
Shims Range
Thickness - mm
Quantity
2.5
—
2.6
—
2.7
—
2.9
—
3.1
—
3.3
—
3.5
—
2.8
—
3.0
—
3.2
—
3.4
—
9. Remove false differential box (s3, s4). Unscrew ring nut (s2) and remove false pinion (s1) and bearing cones (11) and (13).