START-UP
Previous Checkup
a) Is the machine leveled?
b) Voltage and frequency are the same as those on the nameplate?
c) Are the discharges connected and operating?
d) ** If air condensed: Is the air circulation and its temperature appropriate?
** Is water pressure appropriate?
NOTE: In case input water pressure is higher that 0,6 MPa (6 Bar) install a pressure reducer.
THE FAUCETCONNECTION PRESSURE SHOULD NEVER BE REDUCED.
START-UP
Once the installation instructions are followed (ventilation, site conditions, temperatures,
water quality, etc.), proceed as follows:
1. In modular models, remove the top cover to access the installation kit (filters, connection
hoses, etc.)
2. In compact models, open the tank door to access the installation kit.
3. Connect the water hose of the machine to the stopcock.
4. Open the water stopcock. Check that there are no leaks.
5. Connect the machine to the electricity supply and turn on the main switch located on the
front.
6. For the three-phase machine, if the sequence is not correct the red pilot-light will turn on
and it is necessary to change the connection sequence.
7. Check that there is no friction or vibrating element.
8. After 10 minutes of the timer installed in the electrical panel, the machine will be put into
operation. (This delay will happen each time the machine is stopped).
9. In modular models (mainly in three-phase equipment), with the upper cover removed,
check that the motor rotation is in the correct direction.