gyqp g
cable for extending the sensor. Ensure that the sensor can always be replaced in case it fails. The simplest way of doing
so is installing a hidden junction box in which the signal cable is connected to the sensor.
INSTALLING KLIMA CABLE ON WELD MESH:
If using a porous floor finish such as limestone etc. on top of the screed, we recommend that the weld mesh is galvanised
otherwise the rust off the mesh can rise to the top of your finished floor surface during time.
USING THE FLOOR HEATING FOR THE FIRST TIME:
Allow the floor sufficient drying time before you turn on the floor heating. For tiled floors a drying time of 3/4 weeks
after installation should generally be observed. Consult the supplier/manufacturer regarding the applicable drying time
for the product. For sand/cement screed floors a drying time of 1 week per applied cm with a minimum of 4-5 weeks is
generally observed. onsult the supplier/manufacturer regarding the applicable drying time for your situation.
ADJUSTING THE THERMOSTAT:
Timer function: If you have a thermostat with a timer function and want to use it to set the floor drying time make sure you
set a low comfort temperature. (15°C for example). When the thermostat automatically goes on (after the required dry-
ing time) then the comfort temperature may be slowly raised (1°C per day) until the desired comfort temperature is
reached.
Other thermostat / settings: If you have a different thermostat or if you do not want to use the timer function ensure that
you then set the comfort temperature low (15°C for example). After taking the required drying time into account you can
then manually raise the floor temperature with approx. 1°C per day until the desired comfort temperature is reached.