OPERATION
TRANSPORTATION
TRANSPORTATION
TRANSPORTATION PROCEDURE
Selectthe methodof transportationto matchtheweight anddimensions givenin "SPECIFICATIONS (PAGE 5-2)".
Note that the weight and dimensions given in SPECIFICATIONS may differ accordingto other attachments.
LOADING, UNLOADING WORK
WARNING
When loading or unloading the machine, run the engine at low idling
and travel at low speed.
When loading or unloading the machine, park a trailer on a level and
solid roadbed. Moreover keep a good distance between the road
shoulder and the machine.
Make sure that ramps have sufficient width, length and thickness, and
securely fix them, inclined at less than 15°.
If an earth mound is employed, firmly compact it so that the slops will
not collapse.
Remove mud or oil on the undercarriage beforehand so that the
machine will not slip off sideways on the ramps.
Furthermore remove water, snow, ice, grease, oil, etc. from the ramps,
too.
Never try to change the travel direction on the ramps. Otherwise the
machine will slip off them.
Return to the ground or the trailer bed once, and then change the
direction.
Do not operate any other lever than the travel control lever on the
ramps.
The center of gravity of the machine suddenly shifts forward at the
connecting point of the ramps and trailer bed,throwing the machine off
the balance. Pass it slowly for safety.
Be sure to install after unloading the rear view mirror, handrails, step,
etc. that were removed when the machine was loaded. Don not start a
work without them, because it is dangerous, leading to an accident.
When loading or unloading, always use ramps or a platform. Proceed as follows.