14
Figure.4.2-1
Figure.4.2-4
10-30kVA : 500 (for maintenance and internal battery installation)
40-60kVA : 700 (for maintenance and internal battery installation)
700 500 250
A (mm) B (mm) D (mm)C (mm)
Figure.4.2-2 Figure.4.2-3
Climatization
ROOM LAYOUT RECOMMENDATION TABLE
Ventilation
Direction of ventilation is front/sides to back.
The room should be equipped with ventilation system or air conditioning to collect warm air
from the top of the room and provide cool air at the bottom.