Page 95
Applications Using A Single-Stage Thermostat See 
FIGURE 59 for ignition control sequence
B - Heating Sequence -- Integrated Control Thermostat 
Selection DIP Switch 1 ON in “Single-Stage” Position
NOTE - In these applications, two-stage heat will be initi-
ated by the integrated control if heating demand has not 
been  satised  after  the  eld  adjustable  period  (7  or  12 
minutes).
1 -  On  a  call  for  heat,  thermostat  rst-stage  contacts 
close sending a signal to the integrated control. The 
integrated  control  runs  a  self-diagnostic  program 
and  checks  high  temperature  limit  switches  for 
normally  closed  contacts  and  pressure  switches  for 
normally open contacts. The combustion air inducer is 
energized at low speed
2 -  .  Once  the  control  receives  a  signal  that  the  low 
pressure  switch  has  closed,  the  combustion  air 
inducer  begins  a  15-second  pre-purge  in  low 
speed.
NOTE - If the low re pressure switch does not close 
the  combustion  air  inducer  will  switch  to  high  re. 
After a 15 second pre-purge the high re pressure 
switch will close and the unit will begin operation on 
high re. After 10 to 20 seconds of high re operation 
the unit will switch to low re.
3 -   After the pre-purge is complete, a 20-second initial 
ignitor warm-up period begins. The combustion air 
inducer continues to operate at low speed.
4 -   After  the  20-second  warm-up  period  has  ended, 
the gas valve is energized on low re (rst stage) 
and  ignition  occurs. At  the  same  time,  the  control 
module  sends  a  signal  to  begin  an  indoor  blower 
30-second  ON-delay.  When  the  delay  ends,  the 
indoor  blower  motor  is  energized  on  the  low  re 
heating speed and the HUM contacts are energized. 
The integrated control also initiates a second-stage 
on delay (factory-set at 7 minutes; adjustable to 12 
minutes).
5 -   If the heating demand continues beyond the second 
stage  on  delay,  the  integrated  control  energizes 
the  combustion  air  inducer  at  high  speed.  The 
control  also  checks  the  high  re  (second  stage) 
pressure switch to make sure it is closed. The high 
re (second stage) gas valve is energized and the 
indoor  blower  motor  is  energized  for  operation  at 
the high re heating speed.
6 -   When the thermostat heating demand  is  satised, 
the combustion air inducer begins a 5-second low 
speed post-purge. The eld-selected indoor blower 
o delay begins. The indoor blower operates at the 
low-re heating speed.
7 -   When  the  combustion  air  post-purge  period  is 
complete,  the  inducer,  the  HUM  contacts  as  well 
as the 120V ACC terminals are de-energized. The 
indoor blower is de-energized at the end of the o 
delay.
1 stg heat demand
2 stg heat demand
15
ON
OFF
low speed CAI
35
1
Pre-Purge
Ignitor Warm-up
30 second
blower
“on” delay
Post
 Purge
5 SEC80
ignitor
HEATING OPERATION WITH TWO-STAGE THERMOSTAT
low fire gas valve
indoor blower low heat
high speed CAI
high fire gas valve
indoor blower high heat
39
Trial For
Ignition
blower
“off”
delay
 RECOGNITION PERIOD
30 seconds
FIGURE 58 
heat demand
15
ON
OFF
low speed CAI
35
1
Pre-Purge
Ignitor Warm-up
30 second
blower
“on” delay
Post
 Purge
5 SEC80
ignitor
HEATING OPERATION WITH SINGLE STAGE THERMOSTAT
low fire gas valve
indoor blower low heat
high speed CAI
high fire gas valve
indoor blower high heat
39
Trial For
Ignition
blower
“off”
delay
7 or 12 minutes after heating demand begins, furnace switches to high fire (depending on setting)
FIGURE 59