Sequence of Operation -EHO 7.5, 15, 22.5, 30, 45, 60 kW - Y and G, J, M
NOTE: This sequence of operation is for all Electric
Heat kW ratings Y through J voltages. Each step of op
eration is numbered and can be followed in sequence
on the diagrams. Operation for G, J, and M voltages will
be the same.
HEATING ELEMENTS:
1- Terminal Strip TB3 is energized when the unit discon
nect closes. TB3 supplies line voltage to electric heat
elements HE1 through HE7. Each element is protected
by fuse F3.
SECOND STAGE HEAT:
2- Heating demand initiates at W1 in thermostat.
3- 24VAC W2 signal is routed through from the thermo
stat to TB1. After S15 N.C. primary limit and S20 sec
ondary limit is proved, the electric heat contactor K15 is
energized.
4- N.O. contacts K15-1 close allowing the first bank of ele
ments to be energized.
5- Relay K9 is energized. N.O. contacts K9-1 close ener
gizing timer DL2.
6- After a 30-second delay, DL2 closes energizing con
tactor K16.
7- N.O. contacts K16-1 close allowing the second bank of
elements to be energized.
END OF SECOND STAGE HEAT:
8- Heating demand is satisfied. Terminal W1 in the ther
mostat is de-energized.
9- Electric heat contactor K16 is de-energized.
10- The second set of electric heat elements are de-ener
gized.
11- Electric heat contactor K15 is de-energized.
12- The first set of electric heat elements are de-ener
gized.

Other manuals for Lennox LHT Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Lennox LHT Series and is the answer not in the manual?

Lennox LHT Series Specifications

General IconGeneral
BrandLennox
ModelLHT Series
CategoryHeat Pump
LanguageEnglish

Related product manuals