LEAKAGE TEST AND EVACUATION
11
ENGLISH
Vacuum drying of the connecting pipes and the indoor unit
The air which contains moisture remaining in the refrigeration cycle may cause a malfunction on
the compressor.
1 Confirm that both the liquid side valve and the gas side valve are set to the closed position.
2 After connecting the piping, check the joints for gas leakage with gas leak detector.
3 Remove the service port nut, and connect the gauge manifold and the vacuum pump to the
service port by the charge hose.
4 Vacuum the indoor unit and the connecting pipes until the pressure in them lowers to below -
0.8 Torr by the vacuum pump.
5 Remove the valve stem nuts, and fully open the stems of the 2-way and 3-way valves with a
hexagon wrench.
6 Tighten the valve stem nuts of the 2-way valve and 3-way valve.
7 Disconnect the charge hose and fit the nut to the service port.
(Tightening torque: 1.8 kgf·m)