Connecting Pipes
Main cause of gas leakage is defect in flaring
work. Carry out correct flaring work in the
following procedure.
Cut the pipes and the cable.
• Use the accessory piping kit or the pipes
purchased locally.
• Measure the distance between the indoor
and the outdoor unit.
• Cut the pipes a little longer than measured
distance.
Cut the cable 1.5 m longer than the pipe
length.
Burrs removal
• Completely remove all burrs from the cut
cross section of pipe/tube.
Put the end of the copper tube/pipe to
downward direction as you remove burrs in
order to avoid to let burrs drop in the tubing.
Putting nut on
• Remove flare nuts attached to indoor and
outdoor units, than put them on pipe/tube
having completed burr removal.
(Not possible to put them on after flaring work)
Flaring work
Carry out flaring work using dedicated
flaring tool for R-410A as shown below.
Firmly hold copper tube in a bar(or die) as
indicated dimension in the table above.
Check
• Compare the flared work with figure below.
• If flare is noted to be defective, cut off the
flared section and do flaring work again.
Installation Manual 13
ENGLISH
Copper
tube
90°
Slanted Uneven Rough
Pipe
Reamer
Point down
Flare nut
Copper tube
Inclined
Inside is shining without scratches
Smooth all round
Even length
all round
Surface
damaged
Cracked Uneven
thickness
= Improper flaring =
Bar
Copper pipe
"A"
<Wing nut type> <Clutch type>
Preparation of Piping
Connecting Pipes
Pipe diameter
Inch (mm)
A inch (mm)
Wing nut type Clutch type
Ø 1/4 (Ø 6.35)
0.04~0.05 (1.1~1.3)
0~0.02
(0~0.5)
Ø 3/8 (Ø 9.52)
0.06~0.07 (1.5~1.7)
Ø 1/2 (Ø 12.7)
0.06~0.07 (1.6~1.8)
Ø 5/8 (Ø 15.88)
0.06~0.07 (1.6~1.8)
Ø 3/4 (Ø 19.05)
0.07~0.08 (1.9~2.1)