INSTALLATION
WH25
LINDAB SAFE
23/50
Installations within oor
Refer to the section Construction supports characteris-
tics p.17 for further information.
Comply with the minimum distances indicated on section
Minimum distances p.15.
Floor opening
A opening must be provided in the oor as indicated in the
table and in the drawing
Damper positioning
Position the damper in the opening so that the side of the
closing mechanism extends as indicated in the drawing.
Filling
Fill the space between the oor and the damper as indicat-
ed in the table and in the drawing.
Fire resistance classi-
cation
“D” hole size
[mm]
Floor minimum thickness
“S”
[mm]
Sealing
EI 120 S Installation within oor
Floor minimum density 650 kg/m³
EI 120 S
(500 Pa)
From Ø + 25
to Ø + 35
(circular hole)
150 Mortar sealing
EI 90 S Installation within oor
Floor minimum density 650 kg/m³
EI 90 S
(500 Pa)
From Ø + 25
to Ø + 35
(circular hole)
100 Mortar sealing
1. Mortar M-10, EN998-2
D Hole size: see table above
S Floor minimum thickness: see table above
Lp Overlap length between re damper and duct: see section
Dimension p.11
WH25
23/50
LINDAB SAFE