363-205-401 Power Up: NTP-008
Issue 7, March 1997 Page 3 of 4
DO ITEMS BELOW IN ORDER LISTED FOR DETAILS, GO TO
4.
NOTE:
Two
BFU
s are required to turn up each dual bank assembly;
one is needed for the dual bank assembly and the second
one is needed for the associated optical shelves. All 4
BFU
s
should be installed at this time.
DLP-510Install and check fuses in 4
BFU
s (bank fuse units) in optics
power shelf.
5.
NOTE:
Only
AUA11B
or later version
PCU
s should be installed in
optics power shelf.
DLP-530Install 8
PCU
s in optics power shelf.
DLP-5316. Install
A/FCU
(alarm/fan control unit) in optics power shelf.
DLP-5327. Install
AYB1B OU
s in optical shelf.
8. Update Office records.