Fixed grating
Discharge below
fixed grating
(Building Regulation
G3 section 3.61 gives
alternative points
of discharge)
Trapped
gully
Discharge pipe (D2) from tundish,
with continuous fall. See Building
Regulation G3 section 3.56,
Table 4 and worked example
300mm
minimum
600mm maximum
Metal discharge pipe (D1) from
Temperature relief valve to tundish
Tundish
Safety device
(e.g. Temperature
relief valve)
VALVE OUTLET
SIZE
MINIMUM SIZE OF
DISCHARGE PIPE D1
MINIMUM SIZE OF
DISCHARGE PIPE D2
FROM TUNDISH
MAXIMUM RESISTANCE
ALLOWED, EXPRESSED
AS A LENGTH OF
STRAIGHT PIPE (I.E. NO
ELBOWS OR BENDS
RESISTANCE CREATED BY
EACH ELBOW OR BEND
G 1/2 15mm 22mm
28mm
35mm
UP TO 9m
UP TO 18m
UP TO 27m
0.8m
1.0m
1.4m
G 3/4 22mm 28mm
35mm
42mm
UP TO 9m
UP TO 18m
UP TO 27m
1.0m
1.4m
1.7m
G 1 28mm 35mm
42mm
54mm
UP TO 9m
UP TO 18m
UP TO 27m
1.4m
1.7m
2.3m
Discharge Pipework









G3 Requirement


Notes:
1) Discharge pipe-work D2 can now be a plastic pipe but only pipes that have been tested to a
minimum110°C must be used.
2) Discharge pipe D2 can now be plumbed in the soil stack but only soil stacks that can handle
temperatures of 99°C or greater should be used.
Table 5 Sizing of copper discharge pipe “D2” for common T&P Relief Valve sizes.
Figure 10 - Schematic discharge pipe arrangement

