-I Atom B Series VRF 50/60Hz
97
Part 3 - System Design and Installation
box continued from previous page
Step 4
· Open the three valves on the pressure gauge to begin charging refrigerant.
· When the amount charged reaches R (kg), close the three valves. If the amount charged has not reached R (kg)
but no additional refrigerant can be charged, close the three valves on the pressure gauge, run the outdoor unit
in cooling mode, and then open the yellow and blue valves. Continue charging until the full R (kg) of refrigerant
has been charged, then close the yellow and blue valves. Note: Before running the system, be sure to complete
all the pre-commissioning checks as listed in Part 3, 10.2 “Pre-commissioning Checks” and be sure to open all
stop valves as running the system with the stop valves closed would damage the compressor.
Figure 3-7.1: Charging refrigerant
Pressure gauge