Installation
 Page 103 
Pipe diameter
(inch(mm))
Flare dimension A (mm/inch)  
Flare shape
Min Max
1/4" (6.35) 8.4/0.33 8.7/0.34
R0.4~0.8
4
5
°
±
2
90
°    
 
±
4
A
3/8" (9.52) 13.2/0.52 13.5/0.53
1/2" (12.7) 16.2/0.64 16.5/0.65
5/8" (15.9) 19.2/0.76 19.7/0.78
3/4" (19) 23.2/0.91 23.7/0.93
7/8" (22) 26.4/1.04 26.9/1.06
 • After flared the pipe, the opening part must be seal 
by end cover or adhesive tape to avoid duct or exog-
enous impurity come into the pipe.
7. Drill holes if the pipes need to pass the wall.
8. According to the field condition to bend the pipes so 
that it can pass the wall smoothly.
9. Bind and wrap the wire together with the insulated pipe 
if necessary.
10. Set the wall conduit
11. Set the supporter for the pipe.
12. Locate the pipe and fix it by supporter
 • For horizontal refrigerant pipe, the distance be-
tween supporters should not be exceed 1m.
 • For vertical refrigerant pipe, the distance between 
supporters should not be exceed 1.5m.
13. Connect the pipe to indoor unit and outdoor unit by 
using two spanners.
 • Be sure to use two spanners and proper torque to 
fasten the nut, too large torque will damage the 
bellmouthing, and too small torque may cause 
leakage. Refer the following table for different pipe 
connection.
Pipe Diameter
Torque
Sketch map
N.m(lb.ft)
1/4" (6.35)
15~16
(11~11.8)
3/8" (9.52)
25~26
(18.4~19.18)
1/2" (12.7)
35~36
(25.8~26.55)
5/8" (15.9)
45~47
(33.19~34.67)
3/4" (19)
65~67
(47.94~49.42)
7/8" (22)
75-85
(55.3-62.7)
7.  Vacuum Drying and Leakage 
Checking
7.1  Purpose of vacuum drying
 • Eliminating moisture in system to prevent the phe-
nomena of ice-blockage and copper oxidation.
          Ice-blockage shall cause abnormal operation of  
           system, while copper oxide shall damage 
           compressor. 
 • Eliminating the non-condensable gas (air) in system 
to prevent the components oxidizing, pressure fluc-
tuation and bad heat exchange during the operation 
of system. 
7.2  Selection of vacuum pump
 • The ultimate vacuum degree of vacuum pump shall 
be -756mmHg or above. 
 • Precision of vacuum pump shall reach 0.02mmHg or 
above. 
7.3  Operation procedure for vacuum 
drying
Due to different construction environment, two kinds of 
vacuum drying ways could be chosen, namely ordinary 
vacuum drying and special vacuum drying.
7.3.1  Ordinary vacuum drying
1. When conduct first vacuum drying, connect pressure 
gauge to the infusing mouth of gas pipe and liquid pipe, 
and keep vacuum pump running for 1hour (vacuum 
degree of vacuum pump shall be reached -755mmHg).
2. If the vacuum degree of vacuum pump could not reach 
-755mmHg after 1 hour of drying, it indicates that there is 
moisture or leakage in pipeline system and need to go on 
with drying for half an hour. 
3. If the vacuum degree of vacuum pump still could not 
reach -755mmHg after 1.5 hours of drying, check whether 
there is leakage source. 
4 . Leakage test: After the vacuum degree reaches 
-755mmHg, stop vacuum drying and keep the pressure for 
1 hour. If the indicator of vacuum gauge does not go up, 
it is qualified. If going up, it indicates that there is moisture 
or leak source. 
7.3.2  Special vacuum drying
The special vacuum drying method shall be adopted when: 
1. Finding moisture during flushing refrigerant pipe. 
2. Conducting construction on rainy day, because rain