Page 16
Molnar 4 Post Hoist SM4X0
27. For the final levelling of the platforms, raise the platforms to the 4
th
from bottom lock position and
then press the lock button. Pull the cables in each of the 4 posts evenly and tighten the cable end
bolts with a spanner.
NOTE! It is very important to recheck the levels with the heaviest vehicle available (under the hoist
capacity of 4000, 5000, or 6000kg depending on model)
28. Install the other top post covers and the transvers beam pulley covers.
29. Assemble the run-up ramps and lift into position on the platforms and slide the pins through and fit
circlips.