INSTALLATION CHECKLIST
Is the safety cut-off mounted correctly and functioning?
Is the safety cut-off triggered by pressing the red button?
Is the load valve correctly installed?
Is the pump installed on the correct side of the load valve (i.e. towards the
boiler)?
Is the boiler temperature sensor properly mounted?
Is the boiler temperature sensor sufficiently secured?
Is the inside of the boiler dry?
Is a draft stabilizer mounted?
Does the chimney function under all draft conditions?
Measured chimney draught with system at full power.
Chimney data plate fitted / position.
Does the boiler room have the correct size and permanently open fresh air
intake? (building regs part J)
Has the system been ’quick calibrated’ by weighing the pellets?
Weight of pellets in 6 minutes.
Has the client been informed about the importance of weighing the pellets, how
to weigh the pellets, and how to perform the operation using the controller?
Are the burner fan and pellet dosing (chimney draught) settings appropriate?
Is there an owner’s manual available in the boiler room?
Has the client been informed about the location of the burner grate?
Has the client been informed about boiler maintenance procedures and how to
remove and insert the boiler’s cleaning system?
Has the client been informed on how to change the photo sensor? YES NO
Has the client been informed on how to change the igniter? YES NO
Has a CO detector been installed to manufacturer’s instructions?
Comments
Remedial action
required