39
11 De-commissioning
This chapter is intended for installers
This section describes the de-commissioning procedure of the PowerRouter unit.
The PowerRouter must be de-commissioned for repair or disposal.
Shutting down procedure:
1. Switch the On/Off switch to OFF
2. Disconnect DC- and AC-lines using breaker-switches, switches or disconnects.
3. Wait 5 minutes for de-energizing.
Figure 27 PowerRouter fully disconnected and de-energized
OFF
1
2
2
2